Period of Performance: February 2023 to July 2023
Scope: GCC provided weekly schedule updates based on the existing Master Schedule.
Major Stakeholders: Pinner Construction, and Port of Long Beach Construction Management Division, Long Beach Fore Department
Project Description: GCC provided Partnering Facilitation services and weekly schedule updates based on the existing Master Schedule.
The new Fireboat Station #20 Project involved the construction of a two-story fire station building, fireboat bay enclosure, floating dock, positioning and fender piles, retaining walls, emergency generator and additional site improvements.