JFK Bergen Substation

“Delivering safe, reliable, and resilient power distribution for JFK airport.”

Period of Performance: September 2021(Ongoing)

Scope: GCC was contracted by Grace Civil Construction to deliver facilitated Partnering for the new JFK Bergen Substation, located at JFK Airport, NY, on behalf of the Port Authority of New York and New Jersey.

Major Stakeholders: Including the Port Authority of New York and New Jersey, Haugland Energy, Syska Hennesy Group, CHA, and Grace Civil Construction.

Project Description: The Bergen Substation Replacement Project replaces the existing Bergen and Van Wyck 5-kilovolt (5KV) electrical substations at John F. Kennedy International Airport with a new, single Bergen 5KV Substation. The Bergen Substation is a critical component of the electrical power distribution system at JFK and assists in supplying power to JFK airside-landside facilities and associated supporting infrastructure. The Project also includes the decommissioning and demolition of the existing Van Wyck substation, with an option for the decommissioning and demolition of the existing Bergen substation following commissioning of the new Bergen Substation.

Project Gallery

VA CFM – Madison VAMC

GCC team is providing professional support services to Veteran Administration Medical Center in Madison, Wisconsin.  The support services include the construction management of the Electronic

VA CFM – Minneapolis VAMC

Our GCC team is providing professional support services to the Minneapolis VA Health Care System, Minnesota.  The support services include the construction management of the

VA CFM – Tomah VAMC

GCC team is providing professional support services to Veteran Administration Medical Center in Tomah, Wisconsin.  The support services include the construction management of the Electronic

VA CFM – Hampton VAMC

GCC provides Construction Management Services supporting the Veterans Administration Construction and Facilities Management (VA CFM) Team for the Hampton Veterans Administration Medical Center (HAMVAMC) at

LAWA RSI

Los Angeles World Airports (LAWA) is conducting a 7-year Residential Sound Insulation Upgrade program, providing an opportunity for current owners of noise-impacted dwelling units in

New US Embassy Compound

Period of Performance: Ongoing Scope: GCC was contracted by Caddell on behalf of the Department of State, Overseas Buildings Operations (OBO) to deliver facilitated Partnering