Orthopedic Institute For Children

Orthopedic Institute For Children

Orthopedic Institute For Children

 
 

Orthopedic Institute for Children (OIC) renovation project. This project includes the renovation of a 5-story building including abatement, A/C AHUs replacement, electrical upgrade, fire alarm and firefighting systems upgrade, new elevator, restrooms upgrade and all ceiling, wall, and floor finishes. GCC is providing senior management input in supporting on-site project team to resolve contractor’s progress issues, cost alignment with budget and general guidance to site team.

GCC team examined the baseline schedule and found few discrepancies that threatened the completion of the project on time. Several sessions were held and revisions to the schedule lead to ensuring the project is on track. In order to meet milestone completion of works, pull planning session was conducted identifying all activities and their prerequisites in relation to each other to ensure each trade is aware of their tasks and reconfirm their commitment to meet the respective timelines. Cost analysis was also conducted to examine the adherence to the contractual Guaranteed Maximum Price (GMP), enabling the owner better control over the construction contingency budget